Exergen Methuen

This was DCM’s first construction project. Coming off an initial phase of construction that Tom Dube completed with a former employer, this Phase 2 included a large VFD driven ventilation fan and associated ductwork in the manufacturing area, creation of a new kitchen area with millwork, lighting upgrades, door / access improvement for employee and material flow, and a few architectural upgrades and repairs.

Project Stats

  • Negotiated Bid / General Contracting
  • Design – Ci Design / Avid Engineers
  • $263,000
  • 6 weeks
  • DCM self-performed demo, carpentry, and door installation